We welcome as members individuals and organisations who care for Hammersmith
As a Member, you will receive regular updates outlining our activities, giving you the opportunity to participate in consultations and campaigns. We'll invite you to our Awards Evening and AGM, and other events. Members are always encouraged to take an active part in the work done by the committee – come along and see if you can help.
The membership year runs from 1st Jan, and only costs £6 for individuals, £8 for couples or families, and £15 for organisations. Additional voluntary donations always welcome.
Grade II* listed, designed by Sir Joseph Bazalgette, 1887. Closed to motor traffic on 10 April 2019, & completely on 13 August 2020 over safety concerns. Reopened to pedestrians 17 July 2021. ETA repairs for motorised traffic 2027!
Closed to motor traffic: |
Attached is this year’s Chairman’s Annual Report, reviewing the key activities of the Society, plus a look at emerging trends in Hammersmith.
Subjects include:
The agenda, accounts and other AGM information are on the dedicated 2024 AGM page.
You’ll probably have noticed a drilling rig in the river adjacent to the bridge in recent weeks. We understand that in addition to geotechnical bores through the main piers, the rig is in the river to drill bores to investigate the riverbed strata to understand just how strong it is, if and when the Foster-COWI temporary bridge goes ahead.
While the relevant people and equipment are onsite, bores are also being drilled into the foundations alongside Digby Mansions, to ensure the chain anchorages and bridge abutments are in good shape. So far it appears that Bazalgette and his predecessor, Tierney Clark, did good enough jobs, and the foundations can take the extra loads.
The separate ‘stabilisation’ works are progressing, as we reported before, the concrete has been poured into the troublesome pedestals. However, there have been delays in getting the steel support frames built and ready to lift the main bridge chains, allowing the bearings to be replaced. That work is yet to start, which means that the delayed schedule for the bridge to open to cyclists this month looks like it’ll stretch out further. We don’t have a schedule yet for when the bearing replacements will be complete and the bridge reopened, restricted to pedal power.
As far as funding the Foster-COWI proposal and full refurbishments are concerned, the LBHF website says that the ‘business case’ was submitted to the DfT in Dec 2022, and our local and affiliate news page threw up this question from Hansard last week mentioning its ongoing review. It’s not clear how much progress this represents.
Meanwhile, MP’s North and South of the river have spotted an opportunity to ask the government to drop a crumb from the post-HS2 feast to progress the project, while also noting the inevitable cost increase, now to over £200m. More than a crumb then – and we’re hungry for a positive answer.
Continued →
In the last week there have been well-publicised consultation meetings either side of the river, covering the repair and refurbishment of the bridge together with proposed Foster/COWI temporary bridge. Below are photos of the models of the proposals, but there’s one further public exhibition in Barnes this Saturday – details in the diary
We’re delighted to see that the designers have adopted our 2020 proposal to widen the pathways alongside the bridge to at least 2.3m, to better facilitate walking and cycling which are currently rather less than ideal. One of the photos below shows before & after views, and you can see that the visual impact is minimal [click on the images for larger versions]. We understand that Historic England are satisfied that this won’t harm the setting of the Grade 2* bridge.
There’s a further piece of thinking to complete the necessary crossing of both 2-way cycling and pedestrians. Crossings naturally exist under the bridge at each side as we recall from the heights of COVID, but there remains a risk of paths crossing awkwardly. Subject to agreements, there may be an opportunity for the temporary walkway pictured to be part-repurposed into better crossover(s) after completion, with perhaps a smaller scale nod to the recent Dukes Meadows Footbridge.
Continued →
New Civil Engineer recently reported that the bridge stabilisation has progressed and that specialist concrete has been poured into the cast iron pedestals to prevent them collapsing. This means that the bridge is safer for the next stage of repair, which we mentioned in the last email. The stabilisation works are scheduled to complete by the end of February 2023.
It’s worth mentioning again that while the funding arrangement for the rebuilding has been determined, actual funds remain scarce, and the long term funding and maintenance model is undecided. The council prefers to package it up so it can be put into a trust and managed at arms length.
The next step is diversion of a gas main at a cost of £5m, and the letting of contracts so that works on the actual major repairs can begin. We have requested copy of the £200k feasibility report into the Foster/COWI temporary bridge to better understand details of the proposals.
There’s been some press and politics around a proposed bridge toll as a way to close the gap in funding for the rebuild, and whether or not residents would be expected to pay. A historic problem with tolls has been that it cost a significant percentage of the actual toll to collect, and with so much cash sloshing around, there was often significant fraud. Newer technology, such as Automatic Number Plate Recognition (ANPR) would presumably lessen these overheads, if not the displeasure.
We are grateful to the Barnes Bugle for alerting us to a detailed video from Mott’s explaining the whole process for those interested in the technicalities:
Continued →
This slideshow requires JavaScript.
When we last reported on the bridge, the stabilisation works were just about to start. Since then, the council’s contractors have built the ramps to take pedestrians away from the works on the pedestals, and have dismantled the outer casings, completely exposing the troublesome cast iron pedestals for the first time in 135 years, as shown in the photo gallery kindly provided by our member, Jane Bain. Bazalgette’s relatively straightforward design can at last be appreciated, clearly demonstrating the ease with which the pedestals could be replaced by unbolting, as we’ve suggested for some time.
On 28th June, the new Local and Affiliate News page (and homepage sidebar) provided news of the parliamentary adjournment debate initiated by the MP for Putney, Fleur Anderson, and contributed to by our MP Andy Slaughter, and Sarah Olney, MP for Richmond Park, on the subject of bridge restoration funding.
What ensued was a familiar ping-pong between the junior minister on one side, relying on a somewhat worn line that because it’s called Hammersmith Bridge it’s LBHF’s responsibility, and in a pincer movement, MP’s on the other side trying to winkle open the Treasury coffers, making the point that the closure effects are widespread in South West London by reference to Putney Society comments and others, and listing other bridges that are funded in different ways, mostly by TfL, in a ‘policy…all over the place’. It was also made clear that stabilisation work had been started at some LBHF financial risk, given the Task Force delays and machinations around the so-called ‘business case’ that we previously reported.
Worryingly, the business case is now referred to specifically in terms of the stabilisation works, and a further business case is now being requested for the major works to release the established 1/3 government funding. Given unimpeded government largesse elsewhere, and an excessively drawn-out process previously, this might be seen as a further delaying tactic, the politics of which are unclear. The point was made that a similar debate with a similar ping-pong & result occurred a year ago, and that the current TfL funding crisis is hardly helping matters, given its 1/3 agreed funding responsibility. The full debate text is here.
Reference was made to the Prior Information Notice (PIN), which we tweeted at the end of May for expressions of interest in the full restoration works, providing us the hope and expectation that a contractor and plan can be primed, notwithstanding funding. New Civil Engineer reports that 28 organisations have expressed an interest.
Continued →
It’s been a relatively quiet six months at the bridge since we last reported on it. LBHF announced the award of a 9-month stabilisation contract to deal with cracks in the cast-iron pedestals, at a cost of £8.9m, and there’s been some to-ing and fro-ing on who’ll pay (finally equally split LBHF, TfL, DfT), setting aside the cost of the future major repairs necessary, still undecided. The stabilisation will enable the main repair and renewal of other components of the bridge to follow in a separate contract.
During the stabilisation contract cyclists will not be allowed on the main carriageway but must wheel their bikes on the walkway – hoardings have gone up to that effect, though social media suggests that the dismounting instructions have yet to reach all quarters!
We noted late last year that the council had observed planning niceties by applying to itself for permission for the stabilisation works under ref 2021/03680/LBCHF. which it formally approved at the end of February. We understand similar has happened on the South side with LBRUT. Subsequently, an application has been lodged for temporary removal of sections of the handrail to allow pedestrians/cyclists to still cross while bypassing the pedestal housings, under 2022/00786/DLBC.
We remain a little disappointed that the plan still involves pouring concrete into the now infamous cast iron pedestals – not recognised bedfellows – but this is an old comment that has so far been met with a tin ear. We must hope the thermal effects and regular bridge vibration which have been written about at length, and even reported by a concerned member of the public last week, don’t gradually separate or crumble this unusual mixture. If it was a recognised and tested process, a standard method statement would be referenced, but instead the designer has listed an array of materials and notes on the drawings, the word “suitable” signposting a degree of conjecture. We can find no risk assessment to cover the effect of the additional mass, in the light of concerns about the strength of the pedestal footings noted during earlier investigations. The figure mentioned was 6 tonnes per pedestal, and it would be sensible to properly address this risk.
The documents state that Historic England is satisfied that the proposal respects Bazalgette’s design because the pedestals are not visible, which was precisely the point we made last year. If invisible, then remove them and do the job properly as a self-respecting engineer such as Bazalgette would do, having recognised a design or material weakness, and with the existence of better modern materials. Replacing them with something stronger, lighter, maintainable, and built offsite, allowing a quick like-for-like replacement (12 bolts), and future bearing maintenance, without all the onsite paraphernalia and disruption now planned, is the right thing to do, and also cheaper – especially long-term. The existing plan falls into the unfortunate category of being neither fish nor foul – not comprehensive enough to improve function, future maintenance and de-risk the structure, not quick or cheap enough to say it’s a disposable fix until major repairs can be undertaken.
The repair and renewal contract involves replacing 172 hangers, repairing the bearings at the top of the four towers and dealing with defects in many other components to restore the bridge to its former glory, strength and usefulness. There are two options for providing a temporary crossing for the public during this repair work:
The Foster scheme on which we reported last year, involving a ’tube’ structure within the Heritage bridge passing between the towers and allowing the progressive replacement of bridge sections and components.
Continued →
The bridge reopened on the 17th July to some small fanfare. This was after the council’s appointed engineers had blast cleaned the cast iron pedestals so that they could be fully examined for cracks, and the case for continued safe operation could be made.
There are cracks evident in all pedestals to a lesser or greater degree, but they are now assessed as not being critical to structural integrity, provided that the pedestals are not overstressed, which means minimising the movement of the chains that run over them.
The temporary solution, which allows the current limited use by pedestrians and bikes, is to heat or cool the chains that run over the pedestals to maintain temperature, so as to keep them in approximately the same place avoiding excess pedestal stress. This is obviously a 24×7 energy-intensive business, a least-worst solution for the time-being. It’s worth noting that even with only pedestrians and bikes crossing, the bridge still sways a little, it is very much a live structure. The current and much reduced-cost proposal for shoring up the bearings on top of the pedestals (“stabilisation works”) is to replace them with elastomeric sliding bearings, at a total cost of around £6m as widely reported, a figure that doesn’t seem unreasonable. Others can judge whether this is a good enough solution for the long term. We’d prefer to be without the nagging doubts of the hidden cast iron bolted-in parts in critical structural positions, to allow the engineering of a robust 100-year + solution using easily replaceable bearings. This wouldn’t be expensive in the scale of the total repair bill, and as we described early this year, fixing the recurring problem effectively for good.
Without going into further exhaustive detail, which can be found in the references listed below, the main issue remains who will pay for the repairs. The most sensible option is to substantially dismantle the existing bridge with the COWI-Foster structure, or other temporary bridge in place for the duration. This would allow it to be properly repaired to a higher quality than can be achieved onsite, including replacing the troublesome cast iron, and might be quicker overall. Consideration should also be given to lightening the structure via a lighter/improved roadway as we’ve mentioned before, so as to lower bridge loadings, potentially raise capacity a little, and we’d very much like to see wider pathways for pedestrians & bikes.
The latest update from the Task Force shows that our council leader and the newly re-appointed government minister responsible, Baroness Vere, are again at loggerheads, this time over the relatively small sum of £6m for stabilisation works, which is why they haven’t started. If they can’t agree on this, how ever will they agree on the £100m+ full repair bill ? We call for a ceasefire and end to hostilities by letter.
We’re pleased to see that a ferry operator has finally been appointed, and conversely disappointed at a low proposed (peak) capacity of 800/hr. total, i.e. 400 each way, cost – not free – £1.55 proposed, though included in hopper & concessionary fares, restricted operating hours of 6am-10pm, and of course the service delay until later this year.
But as the tale below shows, a temporary bridge was the right solution 140 years ago when the original bridge was falling down through neglect, and remains so today, on the second anniversary of bridge closure.
Accordingly, we wrote to the Prime Minister recently.
Last month we were sent a copy of the lavishly illustrated hardback ‘John Dixon’ by Ian Pearce, published in 2019 (cover shown), which has a fascinating chapter illuminating the design & construction issues of the original Tierney Clark suspension bridge, and its rebuilding as the current bridge, which John Dixon’s company took over in the 1880’s, under Bazalgette and his son Edward.
Readers may order the book direct from the author at the much reduced price of £18 (including UK p&p) using this link.
Here we also need to mention the joint endeavour by the Fulham and Hammersmith, and Barnes and Mortlake Historical Societies in recently updating Charles Hailstone’s 1987 book: A History of Hammersmith Bridge.
To say that the various accounts show history repeating itself would be rather an understatement. Included in Pearce’s book are warnings writ large for those again contemplating tolls and ferries.
A comparative list between then & now:
✔ A toll that irritated residents both sides of the bridge.
✔ Ownership issues preventing adequate finance & oversight.
✔ Lack of maintenance leading to near collapse.
✔ Concerns over bridge loading capacity, weight.
✔ Questionable strength of bridge chains and hangers.
✔ Roadway disintegration.
✔ Use of inappropriate materials for cost reasons.
✔ Engineers reports unheeded, or “disappeared”.
✔ Plan for a temporary ferry with low capacity & limited hours.
❌ Effect on navigation and the Boat Race.
❓ Temporary bridge, 23ft wide with a separate walkway.
It’s of note that Tierney Clark’s Széchenyi Chain Bridge in Budapest, of similar design to his one in Hammersmith and earlier in Marlow, is also currently closed – for repair and rebuilding – not for the first time, perhaps with some familiar issues ?
During Bazalgette’s 1880’s bridge reconstruction, a temporary bridge was built both wide enough for traffic, and with spans sufficient for navigation and to allow the Boat Race to continue as shown here, in response to the inadequacies of a proposed ferry, an outcry from the residents of Castelnau (@TfL take note), and at the time, a statutory duty to maintain a crossing, needing an Act of Parliament to circumvent. Eventually though, the rebuilding was done in just 30 months, and at a cost of £82,177 which is about £10.5M in today’s money.
Continued →
It’s now just over six months since the Bridge was closed to pedestrians and cyclists, and over 22 months since it was closed to traffic, yet there is neither a Bridge repair contract nor an alternative crossing facility in place. Repair work will not progress until there is forward funding to pay the estimated £128M cost (over and above TfL funded temporary stabilisation works). Government funding has been offered conditional on a LBHF contribution of £64M, 50% of the cost, as reported in last weekend’s Observer. This is evidently way beyond the LBHF resources; whilst there has been media reference to the potential of council reserves, the 2019 external auditors report states “…Council do have ongoing financial pressures, which need to be addressed in the medium term… As a result, the Council is now maintaining a reserves position that is below the average when compared to other London Boroughs”. Government funding for local authorities has been considerably reduced in recent years, and an uplift in council tax, aside from social and political issues, would only generate additional income of around £650K per 1% rise.
Hammersmith Bridge would seem to be a unique and most deserving case for special funding, and it is so frustrating that the critical issue of project financing is not addressed in the government Task Force meetings, despite its obvious importance. However we understand that, separate to the Task Force meetings, LBHF have been exploring initiatives which draw on the private sector, not only in the Foster/Ritblat temporary bridge proposal, but also investigating the viability of private funding, secured on an income stream provided by a toll: this financing method which has been used for a number of other UK bridges, including in London, the Dartford Crossing. LBHF residents would be likely to cross toll-free. We understand LBHF have now submitted a comprehensive financial plan to Grant Shapps based on this funding approach. Consideration might be given to 1% of the toll to be set aside for social funding in Hammersmith, similar to the arrangement on the London Eye ticket price.
Some valuable comparative information has emerged regarding the financing of other London bridges. For the recent £9.6M repairs to Albert Bridge, RBKC paid £2.6M in line with many other bridge repairs as recent research indicates, while TfL paid £7M. The £9M refurbishment of Chiswick Bridge was paid for by TfL. Since TfL are out of funds, the recent upgrade of Wandsworth Bridge was paid for by Wandsworth Council – but since the bridge is a simple cantilever structure, fabricated in steel in 1940, the overall cost was only around £6M, less than 6% of the bill for the 1887 Hammersmith Bridge.
These comparative repair costs highlight the unique problems with the bridge, an ornate, Grade II* listed structure constructed from cast iron and wood in 1887, two years after the first internal combustion engine came off the Benz production line. Before the traffic closure in April 2019, over 20,000 vehicles and 2,000 single-decker buses were crossing the Bridge daily; until total closure in August 2020 16,000 pedestrians and cyclists were crossing daily. Until 1998 heavy goods vehicles and double-decker buses were using the Bridge.
The Bridge is clearly not fit for this purpose. If the outward appearance of the Bridge is to be retained, then within the decorative outer claddings the structure has to be not repaired, but replaced, to create a Bridge which is able to sustain the demands of 21st century traffic. We discuss this in more detail in the accompanying article.
Continued →
We’ve made several meaningful and thought-through suggestions in the half-dozen articles, and as many letters to the main bridge protagonists in the last year, from simple widening the pathways to make the bridge more accessible, and to improve public safety, to ways to invisibly fix the 19th century structure for the longer term, in a maintainable 21st century way. Put simply, we believe the current premise for repairs has set the engineers off on a bit of a wild goose chase. While much good work has been done, how much is useful under an alternate premise, and at what opportunity cost ?
As we pass six months since complete closure, we’ve made it crystal clear that there appears very little, if any, value in repairing the much-debated, though normally invisible, cast iron pedestals shown. We continue to be dismayed that so much attention is paid to evaluating and repairing these simple yet demonstrably unsuitable bolted-in components (c.f. Mott MacDonald summary and more detailed Aecom report) when replacement with modern equivalents is an obvious solution. Not only that, but by including, as we’ve suggested, a built-in lifting or jacking mechanism for the chains in a new design pedestal, future maintenance inspections and bearing replacements (the cause of many of the current problems, and certainly the precipitous closure), would be reduced to perhaps scheduled weekend roadway closures every 5 years or so, at low cost and public impact. This, without even considering the environmental and financial running costs of the proposed chain heating and monitoring systems that would no longer be needed.
Surely we can’t be the first to spot such an opportunity for a better and long-lasting engineered solution at lower overall cost – plus the opportunity to cut a whole phase of repair work ? The question is why can we only find passing reference to renewal as an option in the copious Aecom report? Which is where we return to the issue of the premise, assumed to include retaining the original components.
The TfL drawings shown at the public meeting in October, to which we responded, show a temporary support frame for “emergency stabilisation” – already designed – that could be better used during pedestal renewal, using offsite built and tested replacements, instead of a long and expensive (£13.9M + percentage – say half – we don’t have a detailed cost breakdown) of the permanent stabilisation costs, totalling c.£30M.
The current proposal for onsite shoring-up would hardly respect the Grade II* listing, Bazalgette’s design, or materials (assuming that’s the rationale), rendering the pedestals unrecognisable as historic components, especially when infilled with [c. 6 tonnes] of steel fibre reinforced concrete as proposed, and would, according to the Aecom report, leave further nascent cast-iron problems, including a possible failure mode where the cast iron collapses onto the unusual prop/concrete/cast iron mix. The cast iron pedestals would instead make fine museum pieces, to accompany Tower Bridge’s stream engine, removed from service when proven equally obsolete over 40 years ago.
Continued →
One news item from each selected source – more on our Local and Affiliate news page. Subscribe to our weekly highlights
14-storey Tower Block Proposed Next to Hammersmith Gyratory
Queen Caroline Street building would contain 179 rooms for students https://www.hammersmithtoday.co.uk/#!pages/hammersmithtoday:info:ldrsplanning007queencarolinestreet
Council Seeks Comments on Article 4 Direction
Move to change rules on turning office blocks into flats https://www.hammersmithtoday.co.uk/#!pages/shared:common:hfplanning010article4
©2025, The Hammersmith Society | Privacy | Contact | Join | @ Subscribe | ⓘ
Campaigning for over sixty years